Zubair oil field is located in southern Iraq, approximately 20km south-west of the city of Basrah. The onshore oil field, discovered by Basrah Petroleum Company in 1949, contains 4.5 billion barrels of proven reserves.
The field is being redeveloped by a consortium comprising of Eni (32.81%), Oxy (23.44%), KOGAS (18.75%) and Missan Oil Company (25%). The consortium was awarded the field license in October 2009 for a period of 25 years.
Eni, which has the biggest share in the consortium, started operating the oil field in early 2010. The field currently produces about 200,000 barrels of oil per day. The redevelopment project is expected to increase the field’s production capacity to 1.2 million barrels of oil per day by 2016.
Zubair redevelopment project details
Iraq Crude Oil Export Expansion Project, Iraq
Iraq Crude Oil Export Expansion Project (ICOEEP) is a 247km-long pipeline master planned by the Iraqi Ministry of Oil (MoO).
The redevelopment project primarily involves the drilling of more than 200 wells, the construction of treatment and storage facilities, and refurbishment of the existing facilities.
The new oil and gas processing plant will be capable of treating 80,000 barrels of crude oil per day. Six crude oil storage tanks with a capacity of 58,000m³ each will be installed at the site.
A 740MW gas-fired power plant will also be constructed as part of the redevelopment project. Construction of the workers’ site buildings covering a total area of 25,788m² was completed in October 2012.
Contractors involved with Zubair redevelopment project
The front-end engineering design (FEED) studies for the project were carried out by Enereco. The feasibility study for the off-site activities was carried out by Compagnia Technici Ingegneri.
The engineering, procurement and construction (EPC) activities, including the pre-commissioning of the gas and oil separation plant (GOSP) with a capacity of 200,000 barrels per day, was awarded to Samsung Engineering in March 2014. The contract, awarded on a lump-sum turnkey basis, is worth $840m.
A KRW 220bn ($208m) contract for the construction of the oil and gas processing plant was awarded to STX Heavy Industries, while the EPC contract for the installation of new flow tanks was awarded to Rosco. The EPC contractor for the gas-fired power plant is Alstom, which will supply four GT13E2 gas turbines under the €400m worth contract.
The EPC contractor for the early production facility (EPF) is Weatherford International. The process vessels for the EPF will be supplied by Velath, while the API 610 OH2 A-Series pumps will be supplied by Amarinth. Habtoor Leighton Group (HLG) has been subcontracted by Weatherford to carry out certain engineering works and construction of civil, utility and infrastructure facilities the project.
“The new oil and gas processing plant will be capable of treating 80,000 barrels of crude oil per day. “
The EPC contract for the pipeline installations was awarded to Drake & Scull International (DSI), which is carrying out the works in collaboration with Sicim under a contract worth AED 1.31bn ($357m). The contract involves the installation of oil and water flow lines, water trunklines, oil transfer pipelines, wellhead connections and degassing stations.
Dietsmann will provide technical assistance under a contract awarded in August 2012. C.Engineering has been contracted to carry out the implementation and management of the field’s computerised maintenance management system (CMMS).
The workers’ site buildings were constructed by Dorce Prefabricated Building. Sinergia Compression has been subcontracted by Weatherford and STX Heavy Industries to supply lubricated screw compressors and diesel engine reciprocating compressor components respectively.
The precast components for various facilities at the site were designed, supplied and transported by Al-Fayha Group. Termomeccanica Pompe (TMP) supplied 24 centrifugal pumps for the project, while the related seals, couplings, and hydrodynamic bearings are being supplied by John Crane.